On Wednesday, July 06, 2022, the design team met with Muncie
Community Schools to review the progress of the site and floor plan. The site
plan shows replacement of the existing parking lot on the south and adding a
new 53 parking spot parking lot. The new drop off loop allows for 29 vehicles
staged along the drive. The floor plan shows two new classroom additions on the
south side of the east and west wings. There are also plans for an addition to
the admin area to increase the size of the clinic.