Muncie Community Schools received bids on December 20, 2022 from multiple contractors. CORE Construction and Schmidt Associates Inc. has reviewed the bids and provided a recommendation to move forward with the base bid work and accept 5 of the 12 alternates. The alternates that were not accepted are site related with a possibility of adding them towards the end of the project. The contractors have started to submit materials for approval and ordering. The construction trailer and fencing will be delivered and installed in the next couple of weeks. Construction on the new additions will begin in March.