The construction started early Spring at West View Elementary School. During the summer contractors were able to complete the renovation of the restrooms and work in the existing classrooms prior to the kids returning. Most of the masonry and steel structure is complete for the additions. The install of the exterior brick façade has started. The installation of mechanical, plumbing, and electrical systems is in progress on the interior. The project is still scheduled to be completed by the end of 2023.
West View Elementary School Assessment
Tuesday, September 12, 2023
Tuesday, February 7, 2023
Project Status - February 2023
Muncie
Community Schools received bids on December 20, 2022 from multiple contractors.
CORE Construction and Schmidt Associates Inc. has reviewed the bids and
provided a recommendation to move forward with the base bid work and accept 5
of the 12 alternates. The alternates that were not accepted are site related
with a possibility of adding them towards the end of the project. The
contractors have started to submit materials for approval and ordering. The
construction trailer and fencing will be delivered and installed in the next
couple of weeks. Construction on the new additions will begin in March.
Wednesday, December 14, 2022
Project Status - December 2022
The design team has completed the design for the addition and renovation project for West View Elementary School. CORE Construction has distributed the documents to the contractors for bidding. We had a walkthrough on 11/29 for the contractors to see the building. Muncie Community Schools will receive bids on 12/20. Look for the results in the next post.
Tuesday, August 2, 2022
July 27, 2022 - Site Design Meeting
On Tuesday, July 27, 2022, the design team met with Muncie
Community Schools to review the site design. The site design proposed included
two parking lot areas to the South and a separate drop off loop near the gym.
This allows for additional capacity for drop off and parking to the south side
of the building and adds a separation of car riders from the buses. It was
decided during the meeting to look at an option that moved the parking closer
to the building and function as the drop off loop. Schmidt Associates is going
to develop that option for review in the next meeting. The other focus of
discussion was the existing playgrounds and how they are modified for the new
layout. The smaller playground to the east will have a new fence and sidewalk
leading to the entrance. This will help with the safety of the kids with the
added traffic. The west playground will be enlarging its hard surface play area
to the south of the play equipment. The new hard surface will have basketball
goals and the school will stripe the asphalt for additional activities.
July 6, 2022 - Design meeting
On Wednesday, July 06, 2022, the design team met with Muncie
Community Schools to review the progress of the site and floor plan. The site
plan shows replacement of the existing parking lot on the south and adding a
new 53 parking spot parking lot. The new drop off loop allows for 29 vehicles
staged along the drive. The floor plan shows two new classroom additions on the
south side of the east and west wings. There are also plans for an addition to
the admin area to increase the size of the clinic.
Friday, July 15, 2022
Project Kickoff Meeting
On Wednesday, March 16, 2022, Ron Fisher, AIA, LEED AP, and Ryan Benson, AIA led the staff of West View Elementary School through an information gathering process. This process consisted of three parts. The first ten to fifteen minutes allowed each staff member in attendance providing private, individual feedback comments on the current facility. The second ten to fifteen minutes allowed small groups of staff to summarize their individual feedback comments and synthesize them into the top five group feedback comments; the prompt for this group exercise was, “please give us 5 things that you think we should know as we look at the planning for renovations at West View Elementary.” Finally, in the final ten to fifteen minutes, each group was asked to report on their five items. These items were tallied on a flip chart by Ryan Benson. Each time the same or similar item was mentioned, this was also noted. The items on the flip chart represent the summary of the feedback comments from the staff gathered at this event.
The following list indicates the items summarized in the flip charts; a number in parenthesis represents the number of times this items was mentioned by each group.
- Teachers’ Lounge w/ Kitchen (4)
- Accessible Library/Media Center (2)
- Corridor Lockers (1)
- Locker Rooms for sports (1)
- More Staff Restrooms (1)
- Space for indoor recess (1)
- Sensory/Safe Space (2)
- More general storage (3)
- Larger Cafeteria (1)
- Resource/Intervention (3)
- Carpet in Classrooms (1)
- Bigger Nurse Clinic (1)
- Recessed Electrical devices (1)
- Usable Stage for performances (1)
- Age-appropriate Pre-K finishes (1)
All responses, including individual, group, and flip chart
were collected and will be analyzed in the planning for the West View
Elementary School project.
Thanks to all the staff for your participation!
Saturday, March 12, 2022
Blog Foreword
Welcome to the West View Elementary School Blog! The notes and posts that will be included in this blog are the results of field work and community meetings to review and discuss the needs of the school. These posts will represent the work-in-progress and document the discussions that will transpire.